Hoboken to Invest Millions to Upgrade Water Main System




Hoboken, NJ - Thursday, August 4th, 2016

2016-17watermains
The Hoboken City Council voted unanimously yesterday to support a $5.2 million bond ordinance to fund priority upgrades to the city’s water mains.

“We are taking a proactive approach to repairing our century-old water system to make it more reliable and save money in the long run,” said Mayor Dawn Zimmer. “These priority upgrades are in addition to the replacement of the water mains along all of Washington Street and build upon our commitment to improve all aspects of our city’s infrastructure.”

Suez Water conducted an evaluation to identify 50 pipe segments with a total length of 32,200 linear feet (6.34 miles) as the highest priority areas for refurbishment. The analysis considered historical main breaks, conducted a hydraulic evaluation, and included a risk-based prioritization.

The $5.2 million bond would fund the replacement of approximately a third of the highest priority water mains in the first year of the upgrade process. The segments to be upgraded in 2016-2017 include:

• Park Avenue (6th St to 8th St)
• Garden Street (Observer Hwy to 2nd St)
• Garden Street (12th St to 14th St)
• Madison Street (4th St to 6th St)
• River Street (1st St to 4th St)
• Clinton Street (6th St to 7th St)
• Jefferson Street (Newark St to 1st St)
• Grand Street (6th St to 8th St)
• 7th Street (Adams St to Grand St)


###